Ground Improvement to Mitigate Consolidation Settlement Dhoho Airport, KEDIRI

    Home   /   Progress   /   Just Finished   /   Ground Improvement to Mitigate Consolidation Settlement Dhoho Airport, KEDIRI

The Dhoho airport is built on a site with land area of 372 hec- tares of North-West of Kediri city, at the foot of Mount Willis. Most of the platform above the runway has high fill embankment and requires a Ground Improvement to mitigate consolidation settlement.

The design criteria for the maximum settlement due to embankment on the runway are 20mm/1 year and 100mm/10 years and differential settlement must meet the requirements for serviceability of 30mm/45m or 1:1500 based on the Interna- tional Civil Aviation Organization.

For the 23-meter-high fill embankment, the existing soil has been improved using the stone column (SC) method to mitigate consolidation settlement. These works were completed in September 2022.

Client:

Contractor:

Surya Dhoho Investama

LMA Konsorsium