The Puri Indah Hotel Construction Project is a project consisting of a 23-storey hotel tower and a 7-storey parking area tower. Both towers share two levels below ground basement. The primary objective of the project is to accommodate client needs while ensuring the construction is carried out with the highest degree of professionalism and efficiency to complete within the stipulated timeline.

 

The construction will take place in two stages. The first stage will involve the construction of a parking building and two levels of parking basements. The main objective of this stage is to complete the construction by mid-2024 to accommodate the mall that is currently undergoing renovations. Currently, the construction of the parking building’s retaining structure has been completed successfully.

 

The construction of the hotel tower and two levels of basements will take place in the second stage of the project. At present, the design coordination process for the hotel tower is still ongoing.

 

Once both towers and basements are completed, a part of the diaphragm wall between the basements will be demolished to connect the two basements. This will provide easy access and facilitate the movement of goods and services in and out of the hotel.

 

The total Constructed Floor Area for this Project is approximately 46,794 square meters.

Related Projects

Canggu Hotel Batu Bolong

Hotels

Harris Summarecon Serpong

Hotels Retails

Vice President Palace Complex of Nusantara IKN, KALIMANTAN

Offices

Puri Indah Hotel and Parking Building

Hotels Transports

Balmoral Tower Project at Opus Bay, BATAM

Apartments

Hotel at Bandung

Hotels

Cendrawasih Residences, JAKARTA

Apartments

The Pakubuwonos (Signature, Residence, View, House)

Apartments

  • Location

    Jakarta
  • Year

    2024 (Under Design)
  • Client

    PT Antilope Madju Puri Indah
  • Architect

    PTI Architects
  • Building Height Hotel

    94.5 m
  • Building Height Parking

    19.25 m
  • Basement Depth Hotel

    9.5 m
  • Basement Depth Parking

    7.75 m
  • Site Area

    31,485 m²
  • Floor Area Typical Floor Hotel

    831 sq.m
  • Floor Area Parking

    2,325 sq.m
  • Scope of Work

    Foundation Engineering, Geotechnical Engineering and Structural Engineering