The plant is developed by PT. Sumalindo Lestari Jaya (ASTRA Group), a wood-based company, on a 100-hectare hilly terrain land with very soft clay along the riverbank. This project consists of two medium density fireboard plants, with an annual capacity of 100,000 cubic metres each, log yard, power plant building, warehouse, office, housing, infrastructure, and a timber jetty.

 

Davy Sukamta & Partners was appointed as the main consultant for this project. The scope of works included architectural design, structural engineering, geotechnical engineering, and site supervision of the entire development.

 

The construction cost for Plant 1 was 49.70 million USD and Plant 2 was 55.35 million USD.

Related Projects

Schering Indonesia

Industrials

Karawang Logistic Park

Industrials

KITIC Logistic Park

Industrials

MIG Data Center

Industrials Offices

Taman Niaga Warehouse

Industrials

BMKG InaTEWS Jakarta and Bali – Seismically Isolated Structures

Industrials

Sumalindo Medium Density Fibre Board Plant Tanjung Harapan First Phase

Industrials

Previous Project

Next Project

  • Location

    Samarinda, East Kalimantan
  • Year

    1995
  • Client

    Sumalindo Lestari Jaya (member of ASTRA Group)
  • Site Area

    100 ha
  • Scope of Work

    Structural and Geotechnical Engineering